QUESTION 41

As a project manager, you need to ascertain which human resources are involved in the project and Fit Gap documents on the Decision Accelerators.Which two Microsoft Dynamics Sure Step Methodology tree nodes provide this information for the implementation project? (Each correct answer presents part of the solution. Choose two.)

 

A.

Solution Envisioning

B.

Resources

C.

Roles

D.

Deliverables

E.

Preferences

 

Correct Answer: BC

Explanation:

http://download.microsoft.com/download/3/a/c/3ac11404-03a8-4d55-9b90-f789286a4f34/Fit_Gap_Datasheet.pdf

http://vjeko.com/blog/fit-gap-and-solution-blueprint-estimates

http://blogs.msdn.com/b/mvpawardprogram/archive/2012/08/27/microsoft-dynamics-sure-step-methodology-revisited.aspx

http://technet.microsoft.com/en-us/library/aa496439.aspx

 

 

QUESTION 42

You need to perform end-user training in the deployment phase.What are two types of trainers you can use? (Each correct answer presents part of the solution. Choose two.)

 

A.

specialized

B.

deployment

C.

customer

D.

production

 

Correct Answer: AC

Explanation:

A: Some areas of the solution might need high-level specialized trainers.

C: This training can be conducted by customer key users, trainers, or consultants of the consulting implementation team, or by an external third-party vendor

http://technet.microsoft.com/en-us/library/aa496439.aspx

 

 

QUESTION 43

What is the maximum time allocated to a developer task within a sprint cycle?

 

A.

8 hours

B.

16 hours

C.

1 day

D.

30 days

 

Correct Answer: B

Explanation:

http://blogs.msdn.com/b/visualstudioalm/archive/2014/03/03/sample-chapter-scrum-agile-practices-and-visual-studio-from-the-book-adopting-agile-software-practices-from-backlog-to-continuous-feedback-edition-3.aspx#_top

The development phase in agile execution operates according to a Scrum development model. The life cycle is divided to 30-days sprint cycles and daily sprint cycle contains analysis, design, coding implementation and end up with solution test, and finalizing product specification.

Here is how it goes;

Solution Backlog: where the solution feature list is listed

Release Backlog: where identify and prioritize set of features to be developed during 30 day sprint, and identify each feature time estimation (story point),

Sprint Backlog: is the breakdown of release backlog according to feature priority and estimation it could be 3-days to one month (daily sprint)

User story: where descript feature business function, users (roles), and test script (less documentation)

Defect Backlog: where identify and reporting system bugs

Standup daily meeting: what we did (status), and what we have today

 

clip_image001

clip_image002

 

http://social.technet.microsoft.com/wiki/contents/articles/5768.microsoft-dynamics-sure- step-agile-implementation.aspx

QUESTION 44

You completed a Decision Accelerator Offering and need to document the key conclusions.Which group of documents should you use?

 

A.

process review documents

B.

efficiency instruments

C.

customer sign-off documents

D.

validation documents

 

Correct Answer: A

Explanation:

http://download.microsoft.com/download/3/1/E/31EB40F6-AF51-4975-8D1C-52E323C8492A/01-DA-AX_Datasheet_Oct-2011.pdf

http://blogs.msdn.com/b/mvpawardprogram/archive/2012/08/27/microsoft-dynamics-sure-step-methodology-revisited.aspx

http://technet.microsoft.com/en-us/library/aa496439.aspx

 

 

QUESTION 45

What is an objective of diagnostic preparation?

 

A.

to lead an internal kickoff meeting

B.

to gain a preliminary understanding of the customer’s needs

C.

to plan the running of diagnostic accelerators

D.

to prepare high-level project documents

 

Correct Answer: B

Explanation:

http://technet.microsoft.com/en-us/library/aa496439.aspx

 

 

QUESTION 46

You are a project manager for a Microsoft Dynamics implementation.

 

The project is in the deployment phase, and you are planning the final data migration to production.

 

You need to split the effort into two phases: phase one and phase two.

 

How much time should you typically plan between phase one and phase two?

 

A.

one day

B.

one week

C.

two weeks

D.

one month

 

Correct Answer: B

Explanation:

Chapter 6 – Deploying Phase

http://technet.microsoft.com/en-us/library/bb497043.aspx

http://technet.microsoft.com/en-us/library/hh641458%28v=office.14%29.aspx

 

 

 

QUESTION 47

You are a project manager working with a client who has specific feature needs, moderate to complex customizations, and minimal business process mapping completed.You need to recommend a project type for the client.Which project type should you recommend?

 

A.

agile

B.

enterprise

C.

standard

D.

rapid

 

Correct Answer: A

Explanation:

Agile Implementation: Uses an iterative, incremental process for developing Microsoft Dynamics Solutions. This project gives customer greater control over the final solution because customers can quickly change the direction of the solution from one sprint cycle to next.Typically used at a single site requiring specific features and moderate to complex customizations.

References:

http://www.ignify.com/ERP-Implementation-Methodology.asp

http://social.technet.microsoft.com/wiki/contents/articles/5768.microsoft-dynamics-sure-step-agile-implementation.aspx

 

 

QUESTION 48

You are performing the solution envisioning process with a customer. The customer requests that you use all of the Decision Accelerator Offerings. What is the first step you should use in the process?

 

A.

architecture assessment

B.

Fit Gap and Solution Blueprint

C.

requirements and process review

D.

scoping assessment

 

Correct Answer: C

Explanation:

http://download.microsoft.com/download/4/3/D/43D4FED9-54DC-4B3B-95B6-B17A15D1CB8F/03-DA-CRM_Datasheet_Oct-2011.pdf

http://blogs.msdn.com/b/mvpawardprogram/archive/2012/08/27/microsoft-dynamics-sure-step-methodology-revisited.aspx

http://technet.microsoft.com/en-us/library/aa496439.aspx

 

 

QUESTION 49

What functionality does Microsoft Dynamics Sure Step provide?

 

A.

It provides an online toolkit of how to configure Microsoft Dynamics Solutions.

B.

It enables Microsoft Dynamics partners to better serve their customers when implementing Microsoft Dynamics products.

C.

It provides the only way to implement Microsoft Dynamics AX 2012.

D.

It provides Microsoft Dynamics customers project management strategies for the Microsoft Dynamics implementations phase of their project.

 

Correct Answer: B

 

 

Explanation:

“Sure Step is designed to enable the solution provider to better serve customers by helping reduce their Microsoft Dynamics total cost of ownership”

Reference: http://community.dynamics.com/crm/b/lostinthoughtsofcrm/archive/2012/03/17/microsoft-dynamics-sure-step-2012-and-sure-step-online.aspx

 

 

QUESTION 50

During your requirements and process review, you use the questionnaires provided by Sure Step. What is one of the reasons that you use the questionnaire at this stage?

 

A.

to assist in determining the budget of the project

B.

to use as a tool by the partner prior to meeting with the customer

C.

to create detailed process maps

D.

to use as a checklist and a reminder of topics to investigate

 

Correct Answer: D

Explanation:

http://technet.microsoft.com/en-us/library/aa569899.aspx

A questionnaire is a set of questions that is used to collect information for variety of purposes. You can design, create, distribute, and complete questionnaires, and then analyze the results.

You can customize a questionnaire to fit your specific needs by using a combination of the various features that are available in Microsoft Dynamics AX. For example, questionnaires can be used to:

 

clip_image004Test the professional skills of employees and applicants.

clip_image004[1]Test course participants at the end of the course.

clip_image004[2]Evaluate a course, including facilities, content, and instructor.

clip_image004[3]Survey employee and customer satisfaction.

clip_image004[4]Evaluate employee job performance.

 