QUESTION 1

You are a project manager for a Microsoft Dynamics enterprise project.You must hold an executive project kickoff meeting.Which three items should you include on the agenda? (Each correct answer presents part of the solution. Choose three.)

 

A.

consulting practices

B.

training and testing

C.

confirmation of objectives

D.

overview of project vision and objectives

E.

client expectations

 

Correct Answer: CDE

Explanation:

http://technet.microsoft.com/en-us/library/hh852558.aspx

 

 

QUESTION 2

You are responsible for creating and managing projects in a project repository.Which two actions can you perform on existing projects in the repository? (Each correct answer presents part of the solution- Choose two.)

 

A.

clone a project

B.

share a project

C.

change a project type

D.

delete a project

 

Correct Answer: AD

Explanation:

The project properties tab is also used to create new projects, clone projects, and delete projects.

clip_image002

 

http://blogs.msdn.com/b/project/archive/2007/02/24/deliverables.aspx

QUESTION 3

Which customer role is involved in the Fit Gap and Solution Blueprint Decision Accelerator?

 

A.

project manager

B.

key user

C.

business decision maker

D.

executive sponsor

 

Correct Answer: C

Explanation:

http://download.microsoft.com/download/3/a/c/3ac11404-03a8-4d55-9b90-f789286a4f34/Fit_Gap_Datasheet.pdf

http://blogs.msdn.com/b/mvpawardprogram/archive/2012/08/27/microsoft-dynamics-sure-step-methodology-revisited.aspx

http://technet.microsoft.com/en-us/library/aa496439.aspx

 

 

QUESTION 4

Which activity is a precondition for communication management?

 

A.

defining project roles

B.

identifying project stakeholders

C.

analyzing risk

D.

defining project scope

 

Correct Answer: B

 

 

QUESTION 5

What is the Project Management Institute (PMI) definition of a project?

 

A.

A project is unique and contains temporary activities defined by the customer.

B.

A project is a temporary endeavor undertaken to create a unique product, service, or result.

C.

A project is unique and contains a vision, scope, and objectives defined by the customer.

D.

A project is a set of goals and objectives to satisfy a customer’s needs.

 

Correct Answer: D

 

 

QUESTION 6

Which project types does the Microsoft Dynamics Sure Step Model use?

 

A.

waterfall, iterative

B.

diagnostic, analysis, design, development, deployment, and operation

C.

standard, rapid, enterprise, agile, and upgrade

D.

diagnostic, development, and operational

 

Correct Answer: C

Explanation:

The standard set of templates available using Microsoft Dynamics Sure Step Model is standard, rapid, enterprise and agile.

Reference:

http://www.ignify.com/ERP-Implementation-Methodology.asp

http://www.tud.ttu.ee/material/enn/IDU0010/Loeng3Sure_Step/80199A_ENUS_ERP/80199 A_ENUS_ERP/80199_ENUS_ERP_01.pdf(page 5)

 

 

QUESTION 7

Which document is generated as a result of the functional requirements document (FRD)?

 

A.

solution design document (SDD)

B.

Fit Gap Analysis worksheet

C.

functional design document (FDD)

D.

technical design document (TDD)

 

Correct Answer: B

Explanation:

http://dynamicsblog.wordpress.com/2008/10/30/whats-new-in-sure-step-functional-requirements-document/

http://download.microsoft.com/download/3/a/c/3ac11404-03a8-4d55-9b90-f789286a4f34/Fit_Gap_Datasheet.pdf

http://vjeko.com/blog/fit-gap-and-solution-blueprint-estimates

 

 

QUESTION 8

You are conducting the transition from solution to support. Which project phase are you in?

 

A.

quality management

B.

project close

C.

deployment

D.

operations

 

Correct Answer: D

Explanation:

http://technet.microsoft.com/en-us/library/dd572597%28v=office.13%29.aspx

The operations phase is the phase during which you manage operations for Microsoft Office Communications Server 2007 R2 servers, unified communications clients, and unified communications applications that you have deployed in your environment.

 

 

QUESTION 9

Which two components are critical to the success of user acceptance testing? (Each correct answer presents part of the solution. Choose two.)

 

A.

the completion of the end user training

B.

the building of the disaster recovery environment

C.

the usage of user acceptance test scripts

D.

the transactions to use for the tests

 

Correct Answer: AC

Explanation:

A: The standard Sure Step process defines that end user training is required prior to user acceptance testing.

C: Together with the key users, we can now prepare the user acceptance test scripts that will guide the UAT (user acceptance testing) during the Deployment phase.

Note:

 

clip_image003

 

http://technet.microsoft.com/en-us/library/aa496439.aspx

 

 

QUESTION 10

You need to create a project by using the Sure Step Project Creation Wizard.Which two properties must you identify in order to proceed? (Each correct answer presents part of the solution. Choose two.)

< b> 

A.

engagement type

B.

product

C.

project implementation phase

D.

product version

 

Correct Answer: AB

Explanation:

1. In the Microsoft Dynamics Sure Step main window, click the Projects tab.

2. Click Project List, and then click Create New Project.

3. On the Sure Step Project Creation Wizard welcome page, click Next.

 

clip_image004

 

4. On the “Add new project data” window, choose a Solution, Product, and Engagement Type. Type your project name and optionally fill in the rest of the fields. Click Next to continue.

Etc.

http://blogs.msdn.com/b/ukax/archive/2012/01/10/sure-step-online-project-wizard.aspx

 