Question No.1

Scenario: Zephyr Enterprises

Please read this scenario prior to answering the question

Zephyr Enterprises specializes in the development of wind turbine blades for use in large- scale commercial wind energy production systems. Zephyr has manufacturing facilities located in Palm Springs, California, Omaha, Nebraska, and Winnipeg, Ontario. Each of these plants supplies a different manufacturer that builds and sells complete systems. The turbine blades are custom engineered to meet each manufacturers design specifications.

Until recently, most turbine blades were fabricated manually using molded fiber-reinforced plastics. However, recent improvements in composite materials, coupled with enhanced automated methods for precision application of materials during the molding process, have led to significant reduction in weight, increase in strength, and greatly improved blade longevity. Zephyr has pioneered the development of a proprietary automated process for continuous extrusion of the turbine blades. Patents have been filed to protect the process, but certain trade secrets must be closely guarded.

Zephyr has a mature Enterprise Architecture organization that is supported by a cross- functional Architecture Review Board. The Chief Information Officer and the Chief Operating Officer co- sponsor the Enterprise Architecture program.

Zephyr has used TOGAF and its Architecture Development Method (ADM) to develop its automated manufacturing processes and systems that are used to design, manufacture, and test the blade assemblies. They have recently updated to TOGAF 9 and have adapted the Zephyr Enterprise Architecture to closely follow the TOGAF 9 framework. All of Zephyrs IT architects have been trained and certified on TOGAF 9.Recently, an architecture project was completed that defined a standard approach for controlling the Automated Test System that is used at each plant to perform final quality assurance tests on each completed blade assembly. The Manufacturing Architecture Board approved the plan for immediate implementation at each plant.

An Architecture Contract was developed that detailed the work needed to implement and deploy the new Automated Test System controller. The Chief Engineer, sponsor of the activity, has expressed concern that a uniform process be employed at each site to ensure consistency.

Refer to the Zephyr Enterprises Scenario:

You have been assigned by the Lead Architect for the Automated Test System controller project to conduct Compliance Assessments at each manufacturing plant.

During the course of the assessment at the Omaha plant, you discover that the Distributed Data Acquisition System they have purchased uses a proprietary Remote Procedure Call (RPC) that utilizes kernel mode threads instead of the user mode threads that are specified in the Architecture Definition Document. In all other respects, the system meets the requirements stated in the Architecture Definition Document and seems to perform correctly.

You have been asked to describe the compliance of this system for the final report. Based on TOGAF 9, which of the following is the best answer?

  1. You observe that all of the features in the Architecture Definition Document have been implemented in accordance with the specification, except for the RPC mechanism. Your recommendation is that the system be described as conformant.

  2. You observe that the system has many features in common with the Architecture Definition Document, and those features have been implemented in accordance with the specification.

    However, you note that the RPC mechanism has been implemented using features that are not covered by the specification. Your recommendation is that the system be described as consistent.

  3. You observe that the implementation of the RPC mechanism has no features in common with the Architecture Definition Document, therefore the question of its conformance should not be considered. Your recommendation is that the system be described as consistent.

  4. You observe that the system meets most of the requirements stated in the Architecture Definition Document and appears to work correctly. However, you note that the RPC mechanism has not been implemented according to the specification. Your recommendation is that the system be described as non-conformant.

Correct Answer: D

Question No.2

Scenario: Global Mobile 1

Please read this scenario prior to answering the question

Global Mobile is a mobile telecommunications company formed through a series of mergers and acquisitions. They are yet to fully integrate the customer service systems for the most recent acquisitions, and as result, customer service has been a major concern for the Chief Technology Officer.

Results for the last two quarters have shown that Average Revenue Per User (ARPU) and the customer retention (Churn) rate have fallen below the industry average. The Corporate Marketing group has published some new findings about customer satisfaction. The customers appear to be switching to Air Light, a competitor, because of superior customer service. Global Mobile actually has better coverage in nearly all markets than Air Light, and good roaming agreements that keep rates low for business travelers. But, customer satisfaction has remained low.

The Business Strategy group and the Enterprise Architecture group have conducted a high-level project to develop the enterprise-wide strategic plan. They have developed a business scenario which contains a good conceptual model of what needs to be done, and also identifies the key requirements. This was used in preparing the proposal presented to the Executive Council and the Corporate Board.

The planning for the program has been underway for several months. Global Mobile has selected TOGAF 9 as the basis for its Enterprise Architecture.

The Corporate Board has approved funding for a multi-million Euro conversion to transition to a packaged Customer Service System. It is anticipated that the overall program will take five years to complete, but there are some tactical projects that can commence immediately to address the situation. The Corporate Board has placed one additional major constraint on the program. In addition to achieving the business outcomes directly related to improving overall customer service within each business unit, the Corporate Board expects the Target Architecture to produce an additional saving of at least 30% over current operating costs through energy efficiency initiatives, virtualization of servers and workstations, and expanded telecommuting and desk-sharing. This Green initiative is intended to become a model for future investments at all company facilities worldwide.

Refer to Global Mobile scenario

You have been engaged as a consultant to advise the Chief Architect on the best ways to approach to the implementation planning activities for this significant business transformation.

Based on TOGAF 9, which of the following is the best answer? (Is this the right answers to

choose?)

  1. You recommend using conventional implementation planning techniques. The horizontal scope of the Green initiative would make the Capability-Based Planning approach used in the organization#39;s TOGAF-based Enterprise Architecture framework difficult to manage and govern. This approach to planning was better applied within the vertical scope of a business unit.

  2. You recommend that the implementation planning activities be conducted using Capability-Based Planning. This is appropriate because the Green initiative is an enterprise-wide plan with a horizontal scope. Its metrics are aggregated at the enterprise level. It is crucial to gain business unit support and cooperation to achieve the broader business outcomes which will benefit all.

  3. The Capability-Based Planning approach used in the organization#39;s TOGAF-based Enterprise Architecture framework is focused on business outcomes. The Green initiative is an infrastructure program that is technical in nature; therefore, it would not be appropriate to use the Capability- Based Planning approach. Instead, the Global Mobile systems development lifecycle approach should be utilized to develop the Solution Architecture.

  4. You recommend using conventional implementation planning techniques. The Capability-Based Planning approach is normally only used in public sector, defense-related programs. This approach is not appropriate for a private sector company.

Correct Answer: B

Question No.3

TP Banking is a strong financial institute with a well-known acquisition history with an internal IT department managing over 100 projects related to infrastructure and services.

The CIO has decided to create an Enterprise Architecture based on TOGAF 9 as reaction to the difficult market conditions. An Architecture Vision and a set of domain architectures were approved. The CIO is asking you (the Lead Architect) to define an Implementation and Migration Plan that realizes the vision already agreed with the stakeholders involved.

Refer to the scenario above

You are leading a group of domain architects and you are working with the corporate PMO, the business strategy team and service operations. You are meeting the stakeholders to clarify how you want to proceed with the Implementation and Migration Plan. Choose one of the following answers

  1. You propose to start collecting the existing deliverables describing the different domains in order to enable the Enterprise Architecture tram to integrate them with the support of the operation management. Every domain architect will then evaluate the impact on the projects already planned for the domain. The single revised plans will be integrated together and consolidated into a strategic implementation and migration strategy defining an IT roadmap.

  2. You communicate the need for urgency. The projects already planned will be cancelled and the implementation of the new architecture vision will be set as first priority. A set of new projects will be defined to implement the new strategy. You will use the requirements from Phases B through D and define new projects for each one of the requirements. The use of defined interoperability architecture guidelines will then enable the project teams to work together and define a set of new point-to-point interfaces.

  3. You describe the concept of Transition Architectures and clarify that the business value can be achieved by all the projects delivering their increments in a coordinated approach. Capability gaps and project dependencies are analyzed for each domain this will then enable the projects to be organized in work packages. You will then agree on the roadmap for the implementation and migration strategy meeting with all the key stakeholders.

  4. You communicate the CIO#39;s will to transform the corporation and then that he#39;s seeking help from the domain architects to do that. The requirements are managed in order to enable every Architect

to participate to the planning that will result in a detailed list of work activities with impact on the IT portfolio of projects. A five year Target Architecture will then be defined and a report will keep track of dependencies and factors assessment.

Correct Answer: C

Question No.4

Scenario: Marona Inc.

Marona Inc is a Fortune 500 Enterprise in the retail industry with retail store components manufacturing units and marketing outlets spanning the globe and having an annual turnover of 20 billion$ with more than 100, 000 employees world wide.

The CEO, CIO and the stakeholders of the ongoing EA projects are concerned about rising costs and as one measure want to do an investigation into the operational aspects of the realized Enterprise Architecture using TOGAF9.

The CIO approaches you as the Lead Enterprise Architect to carry out this exercise the stakeholder had voiced to him the following concerns:

They want to analyze the roles of the top management for each revenue earning service. Moreover, many of the HR related critical Search application component have become extremely slow. This needs to be diagnosed and rectified. Moreover there is no proper tracking of revenue from retail store component products over time. There has also been a lot of unauthorized or unwanted access to many of the critical information.

Hence the mode of access needs to be strengthened and made much more secure.

Another additional concern is the new launches and the progress of each of the launches over time.

Determine which of the following set of viewpoints are most appropriate to analyze and view in order to address this concern of the stakeholders.

  1. (i) System/Functions Matrix

    1. Actor/Role Matrix

    2. Data Entity/Business Function Matrix

    3. Technology Portfolio Catalog

    4. Data Security Diagram

  2. (i) Goal/Objective/Service Diagram

    1. Contract Measure Catalog

    2. Data Dissemination Diagram

    3. Application Communication Diagram

    4. Data Life Cycle Diagram

  3. (i) Location Catalog

    1. Service/Function Catalog

    2. Data Entity/Business Function Matrix

    3. Application Communication Diagram

  4. (i) System/Functions Catalog

    1. System/Technology Matrix

    2. Goal/Objective/Service Diagram

    3. Product Life Cycle Diagram

    4. Data Security Diagram

Correct Answer: D

Question No.5

Scenario:

Please read this scenario prior to answering the question

You are the Lead Enterprise Architect in a company that specializes in the development of wind turbine blades for use in large-scale commercial wind energy production systems. The company has manufacturing facilities located in Illinois, Nebraska, and Manitoba. Each of these plants supplies a different manufacturer that builds and sells complete systems. The turbine blades are custom engineered to meet each manufacturer#39;s design specifications.

Until recently, most turbine blades were fabricated manually using molded fiber-reinforced plastics. However, recent improvements in composite materials, coupled with enhanced automated methods for precision application of materials during the molding process, have led to significant reduction in weight, increase in strength, and improved blade longevity. The company has pioneered the development of a proprietary automated process for continuous extrusion of the turbine blades. Patents have been filed to protect the process, but certain trade secrets must be closely guarded.

The company has a mature Enterprise Architecture organization that is supported by a cross- functional Architecture Board. The Chief Information Officer and the Chief Operating Officer co- sponsor the Enterprise Architecture program.

TOGAF 9 and its Architecture Development Method (ADM) are used to develop the automated manufacturing processes and systems that are used to design, manufacture, and test the blade assemblies.

Recently, a pilot architecture project was completed at a single location that defined a standard approach for controlling the Automated Test System that is used at each plant to perform final quality assurance tests on each completed blade assembly. The Architecture Board approved the plan for immediate implementation at each plant.

Architecture Contracts have been developed that detail the work needed to implement and deploy the new Automated Test System controller for each location. The Chief Engineer, sponsor of the activity, has expressed concern that a uniform process be employed at each location to ensure consistency.

Refer to the Scenario

You have been asked to recommend the best approach to address the Chief Engineer#39;s concern. Based on TOGAF 9, which of the following is the best answer?

  1. You review the applicable Architecture Contract for each location, ensuring that it addresses the project objectives, effectiveness metrics, acceptance criteria, and risk management. In cases where the contract is issued to an external party, you ensure that it is a legally enforceable contract.

    You schedule compliance reviews at key points in the implementation process to ensure that the work is proceeding in accordance with the Architecture Definition. You ensure that the Architecture Board reviews all deviations from the Architecture Contract, and considers whether or not to grant a dispensation to allow the implementation organization to customize the process to meet their local needs.

  2. You create an Architecture Contract to manage and govern the implementation and migration process at each location. For internal development projects, you issue a memorandum of

    understanding between the Architecture Board and the implementation organization. For contracts issued to an external party, you ensure that it is a fully enforceable legal contract.

    You ensure that the Architecture Board reviews all deviations from the Architecture Contract, and considers whether or not to grant a dispensation to allow the implementation organization to customize the process to meet their local needs.

  3. You create an Architecture Contract to manage and govern the implementation and migration process. If the contract is issued to an external party, you ensure that it is a fully enforceable legal contract. For internal development projects, you decide it is adequate to utilize a memorandum of understanding between the Architecture Board and the implementation organization.

    You recommend that if a deviation from the Architecture Contract is detected, the Architecture Board grant a dispensation to allow the implementation organization the ability to customize the process to meet their local needs.

  4. You use the issued Architecture Contracts to manage the architecture governance processes for the project across the locations. You deploy monitoring tools to assess the performance of the completed blade assembly at each location and develop change requirements if necessary.

You recommend that if a deviation from the contract is detected, the Architecture Board should modify the Architecture Contract to allow the implementation organization the ability to customize the process to meet their local needs. As a result, you then issue a new Request for Architecture Work to implement the modified Architecture Definition.

Correct Answer: A

Question No.6

Scenario: Eight Twelve

Eight Twelve has retail outlets throughout North America. An Enterprise Architecture practice already exists in Eight Twelve. Now the CEO and CIO decide that they want to use TOGAF9 to re-architect their Enterprise Architecture to cater to the changing strategies of Eight Twelve to better respond to the changes in the economic and technology environments.

Some of the key issues which need to be addressed in this re-architecting work are:

  1. Since Eight Twelve#39;s retail chain operate 24 hours a day and are expanding to South America and Europe, the retail chain business ecosystem should be able to withstand any unforeseen disruptions which might affect the chain#39;s day to day operations. This is highly critical to ensure high levels of customer satisfaction and thus maintaining and enhancing Eight Twelve#39;s revenue chain.

  2. Dependency between the application components, which are the nerve centers to Eight Twelve#39;s sophisticated range of services both external and internal, and the application platform and technology infrastructure should be minimal. This would facilitate scalability and ease of enhancement of the service offerings.

  3. Eight Twelve uses the ARTS Data Model and the quality of data is of utmost importance for its operation.

  4. Users of the Enterprise Information ecosystem should have an environment which is able to cater to their needs without any undue delays.

Which one of the following set of Architecture Principles do you feel is the most appropriate for these guidelines stated above for the TOGAF 9 architecting work which Eight Twelve is embarking on?

  1. a) Maximize Benefit to the Enterprise b).Data Trustee

    1. Service Orientation

    2. Responsive Change Management

  2. a) Business Continuity b).Data is an Asset

    1. Data is Shared

    2. Requirements Based Change

  3. a) Maximize Benefit to the Enterprise b).Data is an Asset

    1. Data is Shared

    2. Requirements Based Change

  4. a) Business Continuity b).Data Trustee

    1. Technology Independence

    2. Responsive Change Management

Correct Answer: D

Question No.7

Scenario:

Please read this scenario prior to answering the Question

You are serving as the Lead Architect for the enterprise architecture team at the prime contractor for the Dreadnought Unmanned Aircraft System program.

Over the course of this contract, the company has grown rapidly by acquisition and has inherited numerous different procurement processes and related IT systems. The decision has been made to consolidate and reduce redundant procurement processes and systems. The CEO has announced that the company will seek to leverage higher volume discounts and lower related IT support costs by instituting a preferred supplier program.

TOGAF 9 Is used for internal Enterprise Architecture activities, with an iterative approach for executing Architecture Development Method (ADM) projects.

At present, there are no particularly useful architectural assets related to this initiative, so all assets need to be acquired and customized or created from scratch. The company prefers to implement commercial off the shelf package applications with little customization. The CIO, who is the project sponsor, has stated that she is not concerned about preserving existing processes or systems.

The architect-re development project has put in place Its Architecture Capability for this project and has started a number of iteration cycles to develop the Architecture. Some tasks to address concerns related to the Business Architecture have been completed. The next immediate task is to address the Information Systems Architectures.

The Information Systems Architectures must address stakeholder concerns such as:

  1. Which procurement-related business processes are supported by zero, one, or many existing applications?

  2. What non-procurement applications will need to be integrated with any new procurement applications?

  3. What data will need to be shared? Refer to the Scenario

[Note: You may need to refer to TOGAF 9 Chapter 35 in order to answer this question.]

You have been asked to identify the most appropriate catalogs, matrices, and diagrams for this situation.

Based on TOGAF 9, which of the following is the best answer?

  1. in the early iterations of Architecture development, you would describe the Baseline Application Architecture with a System/Function matrix, and describe the Baseline Data Architecture using a Data Entity/Data Component catalog. In the later Iterations of the Architecture Definition, you would describe the Target Application Architecture using Application Communication diagrams and an Application Interaction matrix, and describe the Target Data Architecture with a System/Data matrix.

  2. In the early iterations of Architecture development, you would describe the Target Application Architecture with Application Communication diagrams and an Application Interaction matrix, and describe the Target Data Architecture with a System/Data matrix. In the later iterations of Architecture development, you would describe the Baseline Application Architecture with an Application and User Location diagram and a System/Function matrix, and describe the Baseline Data Architecture with a Data Entity/Data Component catalog.

  3. In the early iterations of Architecture development, you would describe the Target Application Architecture with Application Communication diagrams and an Application Interaction matrix, and describe the Target Data Architecture with a Data Entity/Business Function matrix and a System/Data matrix. In the later iterations of Architecture development, you would describe the Baseline Application Architecture with a System/Function matrix, and describe the Baseline Data Architecture with a Data Entity/Data Component catalog.

  4. In the early iterations of Architecture development, you would describe the Baseline Application Architecture with a Technology Portfolio catalog, and describe the Baseline Data Architecture with a Data diagram. In the later iterations of Architecture development, you would describe the Target Application Architecture with a System/Technology matrix, and describe the Target Data Architecture with a Data Dissemination diagram.

Correct Answer: C

Question No.8

SureFlight Air Carrier has received approval for the acquisition of a regional carrier.

To integrate the new acquisition, a TOGAF based enterprise architecture program has been initiated. The CIO sponsors the activity supported by the Chief Architect.

In Phase A within the initial iteration the CIO wants to ensure that the architecture activities are recognized among the various stakeholders of the enterprise.

Refer to the scenario above

You are a consultant supporting the Chief Architect that should explain how to identify and engage the stakeholders at this stage of the program.

Identify the best answer accordingly to the TOGAF 9 guidelines. Choose one of the following answers

  1. Using the business scenarios technique you would identify supporting and not supporting stakeholders.

    Then you would list the set of viewpoints that are addressing the stakeholder concerns and share these with them.

  2. You first priority is to communicate with the regional carrier stakeholders developing a Communications

    Plan to share main features and discuss opportunities with them.

  3. You conduct a pilot proof of concept during Phase A to demonstrate the technical feasibility to the stakeholders explaining the approach available from your preferred suppliers.

  4. You identify all the main stakeholders on both the acquired carrier and the rest of the enterprise. Using a stakeholder map, you classify and record their power in relation to this activity. You then focus on implementing the relevant viewpoints that can address the concerns of every main stakeholder identified in the stakeholders map.

Correct Answer: D

Question No.9

TotalComms is a telecommunications company formed from the merging of other 2 telecommunication companies. The business operating model has been unified, the TOGAF 9 Architecture Board approved the outline Implementation and Migration Plan the detailed migration planning must know be approved. Your help is needed to work on the migration planning with all the key stakeholders to achieve an agreement.

Refer to the scenario above

You are the Lead Architect asked to describe accordingly to TOGAF 9 the best way to address the following activities:

image

image

The way the migration planning is conducted. What is going to be implemented.

image

image

The stakeholders involved in the implementation. The definition of the deliverables to use

Choose one of the following answers

  1. The Chief Architect will conduct the Migration planning and then share it with the other domain architects.

    The migration plan will be formed by a list of projects, their priority, their costs and a recommendation on how to proceed. After the plan is shared with the Architectural Board members and any observation that may raise incorporated in the plan, any individual project will go in front of the board for the approval for resources for the next project increment. A GANT chart will be included to be used as a roadmap.

  2. The Migration planning will be conducted as a series of steps: confirming and then coordinating the corporate management frameworks involved; establishing clear business value for the deliverables; creating detailed resource estimates for the work to do; define priority of the work, sequence and then the Transition Architectures. After this, an Implementation and Migration Plan can be confirmed. The Portfolio Management, Operations Management and Business Planning teams should be involved in the implementation of the major deliverables. Once these have been completed, regular meetings will be done to enable the architecture to be kept up-to-date.

  3. Implementation and Migration Strategy will be used to define project plans focusing on scope, time and budget. The business value of each project is assessed and Project Managers will prepare submissions to the IT governance Board to ask for their funding and the Lead Architect will be active part of the board. The collection of project roadmaps and plans will be used to detail the EA Implementation and Migration Plan.

  4. This step will be conducted by the Enterprise Architecture team involving Business, Application, Data, Technology, and Security architects. They will implement the Transition Architectures and together will prioritize a list of activities and include the Architecture Building Blocks in an Implementation and Migration Plan and Roadmap. After this, the comments on the deliverables shared with lines of business and the members of the Executive Board are integrated, this to

enable the funding on the Enterprise Architecture work.

Correct Answer: B

Question No.10

Scenario:

Please read this scenario prior to answering the Question

You have been assigned the role of Lead Enterprise Architect for a manufacturing firm that specializes in musical instruments. The firm has been established for over 100 years, operating in North America for most of that time. In the last ten years, the firm has expanded into European markets and will soon establish a market in Latin America. A future expansion into the Asia Pacific region is also planned.

The firm is organized into several business units that each focus on manufacturing particular families of instruments such as brass, woodwind, and percussion. Each business unit has acquired other producers to expand its manufacturing capacity. This has resulted in a complex environment with a high diversity of business and manufacturing systems.

The Enterprise Architecture (EA) program within the firm has been functioning for several years. It has made significant progress in consolidating the technology portfolio and establishing key standards. The CIO and the COO are pint sponsors of the EA program. The EA program is mature, with an active Architecture Board and a well-defined architecture process and standard content templates based on the TOGAF 9 Architecture Content Framework. The EA process framework is well coordinated with the PMO, Systems Development, and Operations functions.

The firm has completed a strategic plan to reorganize its Sales amp; Marketing organization according to the four target geographic markets. One of the goals of this reorganization is to improve the ability of Marketing to collect more meaningful market analytics that will enable each sector to better address market needs with effective marketing campaigns and global product presence.

A Request for Architecture Work to address the goals of the reorganization has been approved. As the architecture team commences its work, the CIO has expressed concerns about whether the firm will be able to adapt to the proposed architecture and how to manage the associated risks.

Refer to the Scenario

You have been asked how to address the concerns of the CIO. Based on TOGAF 9, which of the following is the best answer?

  1. In Phase B, the team should create a set of views that will enable them to identify the factors that will influence the successful introduction of the architecture into the organization. There should then be an assessment of each factor on a maturity scale that will allow the team to gauge the urgency, readiness, and degree of difficulty to fix. These factors can then be used to assess the initial risks associated with the proposed architecture.

  2. In Phase A the team should analyze their risk by completing an Implementation Factor Assessment and Deduction Matrix to identify the particular risks associated with the implementation and deployment. The matrix should include a list of factors to be considered, their descriptions, and constraints that should be taken into account. These factors can then used to assess the initial risks associated with the proposed architecture.

  3. In Phase A, the team should use the Business Transformation Readiness Assessment technique

    to identify the factors that will influence the successful introduction of the architecture into the organization. The assessment should include determining the readiness rating for each factor based on a maturity scale that will allow the team to gauge the urgency, readiness, and degree of difficulty to fix. These factors can then used to assess the initial risks associated with the proposed architecture.

  4. In Phase A, the team should conduct a Business Scenario to identify the stakeholders#39; concerns and the resulting retirements. Once the retirements have been identified, they can be assessed in terms of their risks. The risks should be evaluated in terms of how they could be avoided, transferred, or mitigated. Any risks that cannot be resolved should be identified as residual risks and their disposition should be decided by the Architecture Board.

Correct Answer: C