Question No.61

In an Agile approach, project values are most effectively implemented when they are determined by the:

  1. sponsor

  2. team

  3. project manager

  4. methodology

Correct Answer: B

Question No.62

According to the fundamental principles of Lean Management, errors result from:

  1. Inadequate user requirements and documentation.

  2. Misjudgment made by project teams and operations staff.

  3. Flaws in development and production systems.

  4. Insufficient management oversight of projects and operations.

Correct Answer: C

Question No.63

In Agile projects, the technique in which planning is done at three distinct horizons is known as:

  1. Monte Carlo Analysis.

  2. Portfolio Management.

  3. DelphiTechnique.

  4. Progressive Elaboration.

Correct Answer: D

Question No.64

Which of the following techniques best encourages osmotic communication?

  1. Reviewing requirements frequently with the Product Owner

  2. Having the Product Owner attend daily standups

  3. Inviting the customer to attend every iteration demo

  4. Seating the team members together in a work area

Correct Answer: D

Question No.65

The three questions asked atevery Daily Scrum should be: quot;What have you accomplished since the last Daily Scrum?quot;;quot;What are you planning to accomplish between now and the next Daily Scrum?quot;;and:

  1. What is preventing you from completing your work effectively?

  2. What is yourcurrent performance velocity?

  3. Are you on track to complete assigned story points?

  4. How many story pointswill you complete this sprint?

Correct Answer: A

Question No.66

The advantage of face-to-face collaboration emphasized in eXtreme Programming (XP) is that it:

  1. allows team members to use common language in their design and code.

  2. delays feedback much more than scheduled inspections.

  3. eliminates communication delays and misunderstandings.

  4. allows team members to correct some mistakes on the fly.

Correct Answer: C

Question No.67

What is the role in an eXtreme Programming (XP) project that ensures the right project processes are applied?

  1. Domain Expert

  2. Product Owner

  3. ScrumMaster

  4. Coach

Correct Answer: D

Question No.68

Which of the seven principles of software development is best intended to solve the problem of inventories causing hidden errors in the process?

  1. Fast-Flexible-Flow

  2. Optimize the Whole

  3. Deliver Early and Often

  4. Eliminate Waste

Correct Answer: D

Question No.69

Who is responsible for determining the business value of each feature?

  1. Product Owner

  2. Steering committee

  3. ScrumMaster

  4. Team

Correct Answer: A

Question No.70

Which layer of the product planning structure defines details at the capability or feature level?

  1. Iteration

  2. Roadmap

  3. Release

  4. Wave

Correct Answer: C