[Free] 2019(Nov) EnsurePass PMI PMI-ACP Dumps with VCE and PDF 21-30

Get Full Version of the Exam
http://www.EnsurePass.com/PMI-ACP.html

Question No.21

What is one of the main benefits that Lean portfolio management provides to a business?

  1. Maximizing work-in-progress

  2. Quality and thoughtfulness

  3. Line of sight to business needs

  4. Maximizing multitasking

Correct Answer: C

Question No.22

Information transmission is greatest amongst team members who are working on:

  1. Individual tasks in the same work area.

  2. The same task through pair programming.

  3. The same group of tasks individually.

  4. Different tasks on the same project.

Correct Answer: B

Question No.23

In Agile risk management, a risk burndown chart is best used to:

  1. Qualitatively analyze the probability of a risk occurring.

  2. Track progress on risk reduction of technical risks.

  3. Document the external risks that could impact the project.

  4. Illustrate the project risk profile and new and changing risks.

Correct Answer: D

Question No.24

A user story says that a product must be very fast.During the demo, the Product Owner is dissatisfied with the speed of the product.The most likely reason that this occurred is because the user story was:

  1. Too large.

  2. Not estimated correctly.

  3. Not testable.

  4. Not descriptive of the value.

Correct Answer: C

Question No.25

A business analyst has identified a new risk in an Agile project.What is the best first step the business analyst should take regarding this risk?

  1. Call a meeting with the project manager and senior management to determine how the risk will be managed.

  2. Email the project manager and add it to the risk register so that it is discussed during the next daily standup.

  3. Add the risk in a clearly visible location and ensure it is discussed after the next daily stand up.

  4. Call an immediate meeting with all team members to discuss the newly identified risk.

Correct Answer: C

Question No.26

Which of the following is part of the 12 practices defined in eXtreme Programming (XP)?

  1. Risk management

  2. Small releases

  3. Project management

  4. Project charter

Correct Answer: B

Question No.27

A common estimation unit for Agile projects is:

  1. Lines of code.

  2. Function points

  3. Story points.

  4. Use-case points.

Correct Answer: C

Question No.28

The smallest amount of functionality that delivers customer value is best described as a:

  1. Function point analysis.

  2. Right sized story.

  3. Minimum marketable feature.

  4. Userstory map.

Correct Answer: C

Question No.29

When facilitated and managed well, the primary benefits of a project retrospective should be to:

  1. Increase empowerment and enjoyment for the team.

  2. Identify the most important issues for the sponsors.

  3. Provide an open forum for team member complaints.

  4. Allow the team to get ahead on release planning.

Correct Answer: D

Question No.30

Scrum practices are facilitated by the:

  1. ScrumMaster.

  2. Product Owner.

  3. Project Sponsor.

  4. Scrum team.

Correct Answer: A

Get Full Version of the Exam
PMI-ACP Dumps
PMI-ACP VCE and PDF