Question No.131

An organization adopts Agile practices and implements an incremental delivery strategy.If implemented correctly, the company should recognize improved:

  1. procurement processes by requiring vendors to ship materials as needed.

  2. project cost management by making incremental payments on contracts.

  3. customer satisfaction by specifying project shipping dates in the contract.

  4. project Return on Investment (ROI) by releasing individual features to market.

Correct Answer: D

Question No.132

Which management style does Agile advocate?

  1. Task

  2. Team

  3. Product

  4. Performance

Correct Answer: B

Question No.133

What is the responsibility of anextremeProgramming (XP) customer role?

  1. Testing the daily increments of the software developed

  2. Writing the stories and acceptance tests for each story

  3. Planning and task allocation for the developer and tester

  4. Interacting closely with users and representing the XP team

Correct Answer: B

Question No.134

What is the best description of the relationship between Scrum andextremeProgramming(XP)?

  1. XP is a component of Scrum.

  2. The principles of each are often complementary.

  3. Scrum is a component of XP.

  4. The principles of each are often contradictory.

    Correct Answer: B

    Question No.135

    Following chart lists stories for a release of an Agile project;

    image

    If the team completes Story A, Story B, and 50% of Story C for the first iteration, what is the team#39;s velocity?

    A.

    9

    B.

    10

    C.

    12

    D.

    15

    Correct Answer: A

    Question No.136

    The most powerful capability of Scrum teams is that they:

    1. Work in timeboxed sprints.

    2. Are self-organized and empowered.

    3. Work from a prioritized backlog.

    4. Value individuals and interactions.

Correct Answer: B

Question No.137

A full cycle of design-code-verifyrelease practiced by extreme Programming (XP) teams is called:

  1. Story

  2. Timebox

  3. Iteration

  4. Burndown

Correct Answer: C

Question No.138

During iteration planning, the team is discussing the design for a user story.A team member states that a design document should be started since the system is complex in nature.Another team member responds that in Agile there is no documentation.How should the ScrumMaster respond?

  1. Agree that documentation should be avoided, since it slows the progress of the team.

  2. Explain that interactions are valued over documentation, but documentation is not forbidden.

  3. Ask the manager if the technical processes mandate that designs be documented.

  4. Ask the Product Owner if it is acceptable for the resources to spend time on documentation.

Correct Answer: B

Question No.139

For a critical project, a new team has been formed from various departments.The project manager should start team building by:

  1. Creating a project charter, documenting roles and responsibilities of each member, and sending it to the team members.

  2. Taking the team offsite for icebreaker sessions and other activities to ensure team members get to know each other.

  3. Assembling the team and discussing roles and responsibilities of each member on the team.

  4. Assembling the team and asking the members to achieve a milestone in a small iteration.

Correct Answer: C

Question No.140

Which answer best describes Wide Band Delphi (e.g.Planning Poker) estimating?

  1. Team members provide story estimates individually and discuss their reasoning until a consensus on the estimate is reached.

  2. Team performance on prior projects is analyzed, and actual hours and durations are used to determine estimates for similar user stories.

  3. Team members apply relative sizing to each task, and story points are triangulated based on the other stories in the Sprint Backlog.

  4. Team members assign a realistic and a pessimistic estimate to each story, and points are assigned based on the calculated average.

Correct Answer: A

>