Question No.111

Test-Driven Development (TDD) is a rapid cycle of:

  1. Requirements, coding, and testing.

  2. Testing, coding, and refactoring.

  3. Testing, refactoring, and validation.

  4. Requirements, coding, and refactoring.

Correct Answer: B

Question No.112

What is the first thing that a team should do to estimate user stories for a project?

  1. Sort the user stories according to priority.

  2. Schedule a team meeting to understand them.

  3. Define the story points measure.

  4. Estimate through function point analysis.

Correct Answer: C

Question No.113

In a vision meeting, the vision for the project is defined and presented by the:

  1. management

  2. project manager

  3. customer

  4. project team

Correct Answer: C

Question No.114

A project team estimates that they should complete 30 story points in the current iteration.Partway through the iteration they realize that they will complete 50 story points at their current rate.The team should:

  1. Shorten the iteration to meet the estimated velocity.

  2. Continue to work with the estimated velocity.

  3. Increase their estimated velocity.

  4. Release members to meet the estimated velocity.

Correct Answer: D

Question No.115

Which of the following drivers is the most important factor in determining the order in which stories will be developed?

  1. Relative cost

  2. Customer value

  3. Development effort

  4. Dependencies

Correct Answer: B

Question No.116

Which of the following best represents both a principle of the Agile manifesto and a Lean method of simplicity?

  1. Maximizing the amount of work not done

  2. Delivering early and continuously

  3. Welcoming changing requirements

  4. Deciding at the last responsible moment

Correct Answer: A

Question No.117

Agile project development processes typically:

  1. Encapsulate analysis, design, code, and test within an iteration.

  2. Document each business process individually and in detail.

  3. Use a Gantt chart with well-defined activities, responsibilities, and time frames.

  4. Map the iteration backlog to a Work Breakdown Structure (WBS).

Correct Answer: A

Question No.118

Since the last iteration, the team has grown from six members to 14 members.As a result, in the current iteration, the team room is crowded and uncomfortable during the team#39;s daily standup.It takes the team longer than the ideal amount of time to complete their standup, which creates problems for the team#39;s current schedule.Based on this information, the project manager should:

  1. Move the standup to a conference call format so space is not a problem.

  2. Increase the standup duration and update the team#39;s calendars.

  3. Assign each team member a maximum speaking time for future standups.

  4. Split the team into sub teams and have them schedule separate standups.

Correct Answer: B

Question No.119

When moving to Agile project management, a keyfactor for the project manager#39;s success will be:

  1. shifting from a controlling mindset to a facilitating mindset

  2. directing the work in a more incremental fashion

  3. only assigning tasks for the nextiteration

  4. giving up control and rotating management through the team

Correct Answer: A

Question No.120

Which of the following would be most likely to assist when a customer has difficulty prioritizing stories?

  1. Split the stories into smaller ones to allow the customer to choose the pieces that they want.

  2. Have the team provide guidance into where their priorities lie to the customer.

  3. Provide additional technical details to give the customer insight into technical challenges.

  4. Have the team rewrite the stories with additional details to clarify requirements.

Correct Answer: A