[Free] 2019(Nov) EnsurePass PMI PgMP Dumps with VCE and PDF 291-300
Get Full Version of the Exam
http://www.EnsurePass.com/PgMP.html
Question No.291
An organization is considering a new program. The program has a cost of $1,950,000 and will last for three years. What is the minimum future value this organization should expectto receive from this program if it is initiated and the rate of return is six percent?
A. |
$2,322,481 |
B. |
$1,950,000 |
C. |
$1,950,001 |
D. |
$2,067,000 |
Correct Answer: A
Question No.292
What does CPI value less than 1.0 indicates?
-
Cost overrun for work completed
-
Scheduled performance is great
-
Cost underrun of performance to date
-
Cost for completed work is as per estimate
Correct Answer: A
Question No.293
When is the lessons learned document updated?
-
At closing phase
-
At planning phase
-
Throughout the project lifecycle
-
At execution phase
Correct Answer: C
Question No.294
After program closure, the lessons learned document becomes the part of ?
-
The risk register
-
The company#39;s organizational process assets
-
The program#39;s performance record
-
The program charter
Correct Answer: B
Question No.295
Which of the following can be used to help you or other project managers on future projects?
-
Sponsor
-
Charter
-
Stakeholder
-
Documentation
Correct Answer: D
Question No.296
What is the other name for critical delivery dates?
-
Substantial completion.
-
Phases
-
Flags.
-
Milestones.
Correct Answer: D
Question No.297
Which of the following directs the improvement efforts to those areas that will have the biggest
impact?
-
Gantt chart
-
Flowchart
-
Pareto diagram
-
User Documentation
Correct Answer: C
Question No.298
Which of the following shows the ratio between a task#39;s budgeted and actual costs?
-
To-Complete Performance Index (TCPI)
-
Schedule Variance (SV)
-
Schedule Performance Index (SPI)
-
Cost Performance Index (CPI)
Correct Answer: D
Question No.299
Which of the following increases when one fast tracks the project?
-
Resource
-
Risk
-
Cost
-
Communication
Correct Answer: B
Question No.300
Which of the following can be an effective tool during quality control to help determine the how the problem occurred?
-
Rework
-
Flowcharting
-
Trend Analysis
-
Pareto Diagram
Correct Answer: B
Get Full Version of the Exam
PgMP Dumps
PgMP VCE and PDF