[Free] 2019(Nov) EnsurePass PMI PgMP Dumps with VCE and PDF 141-150

Get Full Version of the Exam
http://www.EnsurePass.com/PgMP.html

Question No.141

You are the program manager for your organization and are working with Tracy, one of the project managers in your program. Tracy is having some trouble understanding the concept of the critical path in her project#39;s network diagram. Which one of the following is the best definition of the critical path?

  1. It is the path that carries the most risk of project failure.

  2. It is the path that reveals the earliest date the project can finish.

  3. It is the path with the most important activities in the project.

  4. It is the duration of all the project activities if the labor is summed.

Correct Answer: B

Question No.142

You are the program manager for your organization and are reviewing several proposed change requests for your program. Mary, a stakeholder, who has made a change request is asking why it is taking you so long to review the change. You tell her that you must perform integrated change control to review each change request. What is integrated change control?

  1. It is the review of the impact of the change on the program#39;s knowledge areas.

  2. It is the review of the impact of the change on the time, cost, scope, and quality baselines.

  3. It is the review of the impact of the change on the program#39;s triple constraints.

  4. It is the review of the impact of the change on the program#39;s Iron Triangle.

Correct Answer: A

Question No.143

Josh is the program manager for his organization and he#39;s leading the analysis for a new program that may be initiated by his company. The analysis is a focus on the return oninvestment for new software that may be created if the program is initiated. What type of a document is Josh likely creating for his company?

  1. Business case

  2. Program charter

  3. Program scope statement

  4. Statement of work

Correct Answer: A

Question No.144

You are the program manager of the MQQ Program. Your program will use equipment and materials that are new to your industry. You have some concerns that there will be delays and waste by your program team because they#39;ve not worked with these materials or tools before. You elect to send the resources that will work the most with these tools through training. The cost of the training in this instance is known as which one of the following?

  1. Indirect costs

  2. Cost of doing business

  3. Direct costs

  4. Cost of conformance quality

Correct Answer: D

Question No.145

Over the life of your program you#39;ve received many change request forms. Some of the change requests have been approved and some have been declined. Where should you record all change requests and their status?

  1. Change register

  2. Integrated change control

  3. Program Management Information System

  4. Change log

Correct Answer: A

Question No.146

What project management term would you associated with a predetermined budgetyou#39;re your program?

  1. Program governance

  2. Constraint

  3. Cost baseline

  4. Assumption

Correct Answer: B

Question No.147

You are the program manager for your organization and working to create the program statement of work for approval by the program director. All of the following information is defined in the

program statement of work except for which one?

  1. Program requirements for resource competency levels

  2. Structure of the program management team

  3. Metrics and qualifications for program acceptance

  4. Location of the program work

Correct Answer: A

Question No.148

You are the program manager of the BHG Program. One of the projects in your program will be using new materials that are somewhat untested. You are worried that there may be delays and waste because the project team is unaware of how to accurately use these materials. You elect to send the people that will be using the new materials through training on how to complete their project work. You also allow them to purchase some of the materials to experiment on their use before the actual project work is to be done. You want to ensure that mistakes don#39;t enter the project. What type of action have you provided in this scenario?

  1. This is an example of a corrective action.

  2. This is an example of quality assurance.

  3. This is an example of a preventive action.

  4. This is an example of team development.

Correct Answer: C

Question No.149

You are the program manager for your organization. A new program is about to initiated and Marcy, your assistant, asks you about the themes that all new programs must map to. All of the following are themes that you can discuss with Marcy except for which one is not a program theme?

  1. Stakeholder management

  2. Requirements analysis

  3. Benefits management

  4. Program governance

Correct Answer: B

Question No.150

Part of program management is to understand how the communication model works in a program. The program manager must be able to effectively communicate with the program team and stakeholders. What component of the communication model is responsible for carrying the message?

  1. Medium

  2. Sender

  3. Decoder

  4. Encoder

Correct Answer: A

Get Full Version of the Exam
PgMP Dumps
PgMP VCE and PDF