[Free] 2019(Nov) EnsurePass PMI PgMP Dumps with VCE and PDF 111-120

Get Full Version of the Exam
http://www.EnsurePass.com/PgMP.html

Question No.111

Part of your job as the program manager is to coach the project managers on their duties and goals. One of the project managers, Holly, is having trouble discerning the difference between quality assurance and quality control. She understands that she needs both to help you reach the program goals. Which statement best describes quality control for a project within your program?

  1. Quality control is a management-driven effort to plan the work properly so the work is done according to plan.

  2. Quality control is an inspection-driven process to keep mistakes out of the customers#39; hands.

  3. Quality control is a management-driven policy to do the work correctly the first time.

  4. Quality control is an inspection-driven process to prove the existence of the requirements.

Correct Answer: B

Question No.112

Which project management meeting allows stakeholders to meet one another and to learn about the project?

  1. Project scope review

  2. Project authorization meeting

  3. Project status meeting

  4. Project kick-off meeting

Correct Answer: D

Question No.113

You are the program manager of the NHQ Program. The program has reached its final deliverable and the certificate of completion has been created for the program. What else should you, the program manager, create at this time?

  1. Life cycle costing estimates

  2. Lessons learned documentation

  3. Operational transfer plan

  4. Program closure reports

Correct Answer: D

Question No.114

Ned is the program manager for his organization and he#39;s considering some new materials for his program. He and his team have never worked with these materials before and he wants to ask the vendor for some additional information, a demon, and even some samples. What type of a document should Ned send to the vendor?

  1. RFI

  2. RFP

  3. RFQ

  4. IFB

Correct Answer: A

Question No.115

If a program has a budget of completion of $550,000, is 25 percent complete, and has spent

$135,000 what is the cost variance (CV)?

A. .99

B. -$2,500 C. $2,500 D. 1.02

Correct Answer: C

Question No.116

Which benefit measurement method considers the value of each time period#39;s return for a project that will create deliverables over multiple time periods?

  1. Net present value

  2. Future value

  3. Present value

  4. Cost-Benefit ratio

Correct Answer: A

Question No.117

Which of the following types of floats are available? Each correct answer represents a complete solution. Choose two.

  1. Half float

  2. Full float

  3. Total float

  4. Free float

Correct Answer: CD

Question No.118

You are the program manager of the YHT Program. You have been working with a vendor in the program but have decided that the contract between your program and the vendor needs to be terminated. What two things must be documented if you wish to terminate a vendor#39;s contract?

  1. Contract and the quality measurements for the vendor#39;s work

  2. The scope verification document and the termination notice

  3. Contract and scope verification process documents

  4. Work that has been completed and uncompleted work

Correct Answer: D

Question No.119

In your program you must adhere to Six Sigma as part of your organization#39;s enterprise environmental factors. There is terminology, reports, and measurements that you are expected to use as part of your program. Six Sigma is an example of what program management process?

  1. Quality control

  2. Process improvement

  3. Scope verification

  4. Quality assurance

Correct Answer: D

Question No.120

You are the program manager of the NHQ Program. You will need to initiate six projects for your program. When should project initiating happen within a program?

  1. Whenever the program needs to initiate projects, it may, as long as the program has not entered the closing processes of the program.

  2. With program execution

  3. With program initiation

  4. With program planning

Correct Answer: A

Get Full Version of the Exam
PgMP Dumps
PgMP VCE and PDF