[Free] 2019(Nov) EnsurePass PMI PgMP Dumps with VCE and PDF 101-110

Get Full Version of the Exam
http://www.EnsurePass.com/PgMP.html

Question No.101

A risk response in a project in your program has actually caused new risks. What term is assigned to the new risks that a risk response has created?

  1. Reactionary risks

  2. Chain risks

  3. Secondary risks

  4. In flux risks

Correct Answer: C

Question No.102

You are the program manager for your organization. You have proposed a program that will cost

$750,000 and will last for four years. Management is concerned with the cost of the program in relation to the return your program will bring. If the rate of return is six percent what is the minimum value your project should return in four years based on the investment of the program?

A.

$750,000

B.

$795,000

C.

$750,001

D.

$946,857

Correct Answer: D

Question No.103

You are the project manager for the JJY Project, which is similar to the HHG Project you managed last quarter. You would like to model the current project scope on the previous project

to save time and effort. This is an example of what kind of scope definition?

  1. Analogous estimating

  2. Organizational process assets

  3. Parametric scope definition

  4. Template driven

Correct Answer: D

Question No.104

You are the program manager for your organization. You are examining the order of the activities in your program schedule and would like to change some of the ordering to alleviate scheduling conflicts, risks, and based on your experience with the discipline the program uses. Some of the activities you can rearrange while some of the activities must be completed in a particular order. What term describes the activities that must happen in a particular order?

  1. Mandatory dependencies

  2. Finish on constraints

  3. Benefits management dependencies

  4. Discretionary dependencies

Correct Answer: A

Question No.105

What quality control chart compares two or more variables over time to determine how closely the variables may be related to one another?

  1. Run chart

  2. Scatter diagram

  3. Control chart

  4. Pareto diagram

Correct Answer: B

Question No.106

All of the following are resources that need to be monitored and controlled except for which one?

  1. Equipment

  2. Staff

  3. Quality

  4. Facilities

Correct Answer: C

Question No.107

What schedule analysis simulation tool allows you, the project manager, to review possible combinations of events such as optimistic, most likely and pessimistic outcomes for your project?

  1. pert

  2. gert

  3. pmis

  4. Monte Carlo

Correct Answer: D

Question No.108

All of the following are resources that you will need to monitor and control in a program environment except for which one?

  1. Staff members

  2. Contracts

  3. Quality

  4. Equipment

Correct Answer: B

Question No.109

You are the program manager for your organization. Your program will create a new condominium in your community. There are several concerns about the condos including the timing, the local economy, the environment, and the proposed schedule. You and your team are creating the program management plan to address these concerns along with identifying the constituent projects that will build the structures and deliverables. What group will need to review your program plan to approve the plan before you may proceed in the work?

  1. The local government

  2. The change control board

  3. The stakeholders

  4. The program board

Correct Answer: D

Question No.110

What cost estimating approach uses the work breakdown structure to create a cost estimate?

  1. Analogous

  2. Definitive

  3. Top down

  4. Parametric

Correct Answer: B

Get Full Version of the Exam
PgMP Dumps
PgMP VCE and PDF