Question No.201

Which of the following is true about the V-model?

  1. It has the same steps as the waterfall model for software development.

  2. It is referred to as a cyclical model for software development.

  3. It enables the production of a working version of the system as early as possible.

  4. It enables test planning to start as early as possible.

Correct Answer: D

Question No.202

Which of the following is true of iterative development?

  1. It uses fully defined specifications from the start.

  2. It involves the users in the testing throughout.

  3. Changes to the system do not need to be formally recorded.

  4. It is not suitable for developing websites.

Correct Answer: B

Question No.203

A top-down development strategy affects which level of testing most?

  1. Component testing

  2. Integration testing

  3. System testing

  4. User acceptance testing

Correct Answer: B

Question No.204

Which of the following is a non-functional requirement?

  1. The system will enable users to buy books.

  2. The system will allow users to return books.

  3. The system will ensure security of the customer details.

  4. The system will allow up to 100 users to log in at the same time.

Correct Answer: D

Question No.205

Which of the following statements are true?

  1. For every development activity there is a corresponding testing activity.

  2. Each test level has the same test objectives.

  3. The analysis and design of tests for a given test level should begin after the corresponding development activity.

  4. Testers should be involved in reviewing documents as soon as drafts are available in the development life cycle.

  1. (i) and (ii)

  2. (iii) and (iv)

  3. (ii) and (iii)

  4. (i) and (iv)

Correct Answer: D

Question No.206

Which of the following statements are correct for walkthroughs?

  1. Often led by the author.

  2. Documented and defined results.

  3. All participants have defined roles.

  4. Used to aid learning.

  5. Main purpose is to find defects.

  1. (i) and (v) are correct.

  2. (ii) and (iii) are correct.

  3. (i) and (iv) are correct.

  4. (iii) and (iv) are correct.

Correct Answer: C

Question No.207

Which of the following has the typical formal review activities in the correct sequence?

  1. Kick-off, review meeting, planning, follow-up.

  2. Kick-off, planning, review meeting, re-work.

  3. Planning, kick-off, individual preparation, review meeting.

  4. Planning, individual preparation, follow-up, re-work.

Correct Answer: C

Question No.208

Which of the following statements are true?

  1. Defects are likely to be found earlier in the development process by using reviews rather than static analysis.

  2. Walkthroughs require code but static analysis does not require code.

  3. Informal reviews can be performed on code and specifications.

  4. Dynamic techniques are generally used before static techniques.

  5. Dynamic techniques can only be used after code is ready to be executed.

A. (i), (ii), (vi).

B. (ii), (iii), (v).

C. (i), (iv), (v).

D. (i), (iii), (v).

Correct Answer: D

Question No.209

Which of the following is most likely to be performed by developers?

  1. Technical review of a functional specification.

  2. Walkthrough of a requirements document.

  3. Informal review of a program specification.

  4. Static analysis of a software model.

Correct Answer: D

Question No.210

Which of the following are most characteristic of structure-based testing?

  1. Information about how the software is constructed is used to derive test cases.

  2. Statement coverage and/or decision coverage can be measured for existing test cases.

  3. The knowledge and experience of people are used to derive test cases.

  4. Test cases are derived from a model or specification of the system.

  1. (i) and (ii)

  2. (ii) and (iii)

  3. (ii) and (iv)

  4. (i) and (iii)

Correct Answer: A